Owner: Brown Machine
Construction Manager: FED Corporation
Design/Assist Team: Brown Machine, FED Corporation, Siedell Architects
Master Electric, Inc.: Doug Smith, Lead Design
Completed: April 2015
Master Electric was hand-selected as a design partner for Brown Machine’s 13,000 sq. ft. F-Bay expansion. The project scope included the extension of existing overhead primary power, the installation of a 3,000 KVA transformer, a 4,000 AMP service, 3 runs of 2,000 AMP bus duct system, HVAC and equipment power, a welder and compressor column power, and crane rail power upgrades.
This project had to be built within the Owner’s limited budget and a strict schedule. Our team delivered on both. We were able to delight this Owner by bringing this project in under budget and turning this expansion over to them in time to start production of their new line.